Milligan Residence: 6-27-08
The interior of the house is still being worked on. The electrician should be finish by Tuesday. Low voltage should be done by Friday.
What’s been done since the last update?
- The septic system installed
- Well installed
- Stucco trim and lath work were completed
- Windows and door removed and reinstalled
- Plumber finished
- Roof tiles loaded
- Pool tiles and coping installed
- Land cleared in the back
- Cut down and reshaped the privacy wall
- Electrician is almost done