June 29, 2008 at 11:25 am · Category: Milligan Residence
The interior of the house is still being worked on. The electrician should be finish by Tuesday. Low voltage should be done by Friday.
What’s been done since the last update?
- The septic system installed
- Well installed
- Stucco trim and lath work were completed
- Windows and door removed and reinstalled
- Plumber finished
- Roof tiles loaded
- Pool tiles and coping installed
- Land cleared in the back
- Cut down and reshaped the privacy wall
- Electrician is almost done
Photos:
May 18, 2008 at 11:58 pm · Category: Milligan Residence
May 12, 2008 at 6:09 pm · Category: Milligan Residence
Given that I had to drive the 105 miles to handle the well and septic permits, I decided to stop by the house to check on things. Here are photos from today.
May 7, 2008 at 6:42 pm · Category: Milligan Residence
We started working on the house again in April. The framing and HVAC rough have been completed. Today the pool began. Here are two photos I took.
May 7, 2008 at 4:59 pm · Category: Milligan Residence
Photo updates
September 8, 2007 at 10:52 pm · Category: Milligan Residence
Lots of work has been done. They finally put the felt on the roof. Most of the framing on the inside has been completed. The electrician started working this week. The house is looking great on the inside. Here are some photos.
August 13, 2007 at 10:39 pm · Category: Milligan Residence
The roof is on and the windows are in. Tomorrow they are supposed to put the sheathing on the roof and install the French doors. This week the framing should being. We found a company to do the screen enclosure and we also modified the pool by removing two feet from its length. Here are some of the photos I took today.
August 3, 2007 at 7:35 pm · Category: Milligan Residence
I spent a few hours designing our new kitchen layout. I did 11 different designs and we decided to go with the one you see below. We have a U-shaped kitchen and here are the two main walls. Let me know what you think.
This drawing has been sent to the kitchen cabinet designers so they can redo it with their software.
July 20, 2007 at 10:55 pm · Category: Milligan Residence
Alright!!! The second floor is up. The house looks massive now. The roof should be on by next weekend.
July 9, 2007 at 2:16 pm · Category: Milligan Residence
After weeks of rain and delays, the sub-floor for the second floor is about ready to be poured. The wood shown in the photos is only to support the floor when its poured.